As of 30 June 2021, environmental energy had invested in 217 projects, commanding a total investment of approximately RMB86.792 billion, and undertook 1 O&M project. These projects are designed to have an annual household waste processing capacity of 49,019,500 tonnes, which is expected to generate annual on-grid electricity of 16,482,010,800 kWh, an annual food and kitchen waste processing capacity of 2,131,600 tonnes, an annual sludge treatment capacity of 321,200 tonnes, and an annual medical waste processing capacity of 10,950 tonnes.

Projects in Operation

Project Daily Processing Capacity
(tonne)
Total Investment
(RMB Million)
Jiangsu Province
Suqian Food Waste Treatment Project Phase I 100 79
Suqian Food Waste Treatment Project Phase II 100 41
Wujiang Food Waste Treatment Project 200 141
Danyang Food Waste Treatment Project 80 63
Shandong Province
Laiwu Food Waste Treatment Project 100 50
Hainan Province
Sanya Food Waste Treatment Project Phase I and Upgrading 100 53
Zhejiang Province
Haiyan Food Waste Treatment Project Phase I 75 65
Anhui Province
Ma'anshan Food Waste Treatment Project 200 150
Liaoning Province
Shenyang Daxin Food Waste Treatment Project 400 115

Suqian Food Waste Treatment Project has a total designed daily food waste treatment capacity of 200 tonnes. It is the first demonstration food waste project designed, manufactured, constructed and operated by Everbright Environment. It has the complete processing chain and operates in synergy with the company's waste-to-energy project in the city.

Laiwu Food Waste Treatment Project has a designed daily food waste processing capacity of 100 tonnes. It was designed, constructed and operated to coordinate with Laiwu Waste-to-energy Project. It is Everbright Environment's first household waste and food waste co-processing project, which has led to higher processing efficiency and lower operating costs.

Sanya Food Waste Treatment Project Phase I and Upgrading has a designed daily food waste processing capacity of 100 tonnes. The project is located adjacent to Sanya Waste-to-energy Project, which creates a synergy to improve the overall project revenues.

Projects in Construction

Project Daily Processing Capacity
(tonne)
Total Investment
(RMB Million)
Henan Province
Ruzhou Food Waste Treatment Project
Phase I
50 30
Tianjin
Beichen Food Waste Treatment Project 200 110
Xiqing Food Waste Treatment Project 200 110
Sichuan Province
Leshan Food Waste Treatment Project 110 80
Hunan Province
Yingtan Food Waste Treatment Project 100 52
Jiangxi Province
Ji'an Food Waste Treatment Project 110 59

籌建項目