Everbright Water's Project Construction Progressing Steadily
A Number of Projects Completed Construction by Year End

Singapore, 29 December 2016 – China Everbright Water Limited ("Everbright Water" or the "Company", SGX: U9E) (中国光大水务有限公司), an environmental protection company focusing on integrated environmental water business, is pleased to announce the completion of several project constructions at the end of the year. These include the completion of construction of Beijing Daxing Tiantanghe Waste Water Treatment Project Phase II and Upgrade ("Tiantanghe Project Phase II and Upgrade"), Pulandian Waste Water Treatment Project Phase II in Liaoning Province ("Pulandian Project Phase II") and Sanmenxia Waste Water Treatment Project Phase I Upgrading Project in Henan Province ("Sanmenxia Project Phase I Upgrading Project"), all of which have started running in compliance with discharge standards. Separately, Nanjing Pukou Reusable Water Project Phase I in Jiangsu Province ("Pukou Reusable Water Project Phase I") has completed construction and has entered into the commissioning phase. Wuzhong Chengnan Waste Water Treatment Project Phase II and Upgrade in Jiangsu Province ("Wuzhong Project Phase II and Upgrade") has also completed construction and commenced commercial operations.

Tiantanghe Project Phase II and Upgrade commenced construction in December 2015. The daily waste water treatment capacity of the project reached 40,000 m3, with a total investment of approximately RMB228 million. The water discharge complies with Beijing's Grade B discharge standard according to the Discharge Standard of Water Pollutants for Municipal Wastewater Treatment Plant (DB11/890-2012), which is more stringent than the National Grade 1A discharge standard. The project has since been completed and started running; it also obtains satisfactory results during the commissioning phase and complies with discharge standards.

Pulandian Project Phase II commenced construction in May 2016. The project has a daily waste water treatment capacity of 20,000 m3, with a total investment of approximately RMB42.46 million. The project has since been completed and has started running; it also obtains satisfactory results during the commissioning phase and complies with discharge standards.

Sanmenxia Project Phase I Upgrading Project commenced construction in September 2016. The project has a daily waste water treatment capacity of 30,000 m3, with a total investment of approximately RMB27 million. The water discharge complies with the national Grade 1A discharge standard. The project was completed recently and has started running; it also obtains satisfactory results during the commissioning phase and complies with discharge standards.

Pukou Reusable Water Project Phase I was constructed on a Build-Operate-Transfer ("BOT") basis, with a designed daily water supply of 20,000 m3. The total investment amounted to approximately RMB47.53 million. The project has since been completed and has started running, with the water discharge complying with the surface water category IV standard.

Wuzhong Project Phase II and Upgrade commands a total investment of approximately RMB220 million. The project commenced commercial operations in July 2016, with a daily waste water treatment capacity of 75,000 m3. The water discharge complies with the national Grade 1A discharge standard.

Mr. Wang Tianyi, Executive Director & Chairman of Everbright Water, said: "Everbright Water has seen a number of projects complete construction at the end of 2016, concluding the work for the year. This lays a solid foundation for the Company's business operations and development in the coming year. We will continue to work hard, push forward the construction of our projects in good order, make sure the projects comply with the discharge standards, and assist to improve the water quality and eco-system of the regions where our projects are located. On the project development front, we will set our sights further in pursuit of new breakthroughs in different regions and new business areas. Looking ahead in the new year, we are confident that we will continue to uphold a strong sense of social and environmental responsibility and work towards greater contributions to the ecological environmental protection and the enhancement of the Company's market leadership position in the environmental water business segment, through high construction standards, safe and stable operations of our projects and also the compliance with discharge standards."